SAHIWAL: The Green Electric Bus has revised the schedule for route EV04004 running between GBS SWL and Adda Kameer, according to PakBus timetable data.

The fare for the route remains Rs20. It has 20 stops in each direction.

The first bus from GBS SWL to Adda Kameer is at 06:00, unchanged, but the last bus has been pushed to 19:12 from 18:50, 22 minutes later. Daily trips on this direction have increased to 13 from 11.

In the opposite direction, from Adda Kameer to GBS SWL, the first bus remains at 06:00 and the last bus is at 21:24. Buses per day have gone up to 15 from 13.

Check the new times and plan your trip on pakbus.app.

EV04004: GBS Sahiwal to Adda Kameer

GBS Sahiwal to Adda Kameer

  • Last bus: 19:12, was 18:50
  • Buses a day: 13, was 11

Adda Kameer to GBS Sahiwal

  • Buses a day: 15, was 13

All Sahiwal routes

Data: PakBus GTFS feed of 14 October 2026.